Construction of a 100 kWp photovoltaic installation in Radomsko

Construction of a 100 kWp photovoltaic installation

Construction of a photovoltaic power plant in Radomsko. Radomsko is a small city located in Lodz Voivodeship, Radomsko County. It is one of the oldest urban centers in Poland, with a rich history and culture. The city has a population of about 60,000 and is one of the region’s main economic centers.

The company that commissioned us decided to invest in the construction of the installation mainly for its own use. High electricity consumption is driving the search for solutions in the face of ever-increasing electricity prices.

The photovoltaic installation we designed and built will allow the company to produce a significant portion of its annual electricity needs.

As a result, the company will be able to cover most of its electricity needs from its own sources. This means it will be able to save money on its electricity bills, as well as contribute to reducing CO2 emissions.

The construction of the photovoltaic farm was preceded by preparations for the venture, i.e. estimating the size of the installation, planning the work, selecting the construction and components, and setting a date for the start of the work. According to the plan, the work was supposed to take up to 2 weeks and we managed to finish the order in just 10 days!
During this time, our team performed the following work:

Building a photovoltaic power plant – what have we done ?

Przygotowanie terenu pod montaż instalacji,
Montaż konstrukcji,
Montaż modułów fotowoltaicznych,
Montaż i konfigurację falowników,
Uruchomienie instalacji PV

The work has resulted in a photovoltaic installation that will produce about 95 MWh of electricity per year. By investing in RES (renewable energy sources), this manufacturing company will significantly reduce its electricity bills.

The installation was based on photovoltaic modules from LONGi Solar, which have an efficiency of up to 18.4%. Huawei’s inverters, which are also part of the overall installation, have been placed under the canopy.

We successfully completed the construction of a solar power plant on the roof of the building, handing over the commissioning instructions, schematics and warranties to the owner.

Construction of a photovoltaic power plant Radomsko – Summary:

Installation power: 100 kWp
Duration of work: 10 days
Installation location: roof

Are you planning to build your photovoltaic farm or looking for an O&M service company?

Do you want to purchase a photovoltaic or wind farm project and need an efficient and professional audit / due diligence?

Are you looking for a photovoltaic panel recycleror cleaning company for photovoltaic installations and farms?

If you are ready to act, so are we!

Call! +48 797 897 895

Leave a Comment

Lighthief

Lighthief is innovation, technology and science in the service of recycling photovoltaic panels and wind farms. The company's topics of interest touch on recovery and recycling in the broadest sense, mainly in the field of RES, or renewable energy sources.

Contact

St. Kazimierza 2B, 42-226 Częstochowa, Poland

biuro@lighthief.com

+ 48 797 897 895

Lighthief {{current_year}}

+48 797 897 895